Parliament Resolution No. 305
AdoptedResolution Urging the Department of Transportation (DOTr) Through the Civil Aviation Authority of the Philippines (CAAP) for Immediate Action on Completing the Renovation of Cotabato Airport and Determine Accountability for Delays
Voted on and adopted by Parliament. Resolutions express its position; unlike an act, most are not binding on outside bodies.
What this measure does
Parliament urges the Department of Transportation (DOTr), through the Civil Aviation Authority of the Philippines (CAAP), to act immediately to finish the renovation of Cotabato Airport, adding personnel, equipment and materials as needed. It asks DOTr and CAAP to monitor the work closely and, if there are further delays, to impose financial penalties or terminate the contract, and to hold the contractor liable for added costs and any damage to airport facilities.
Copies go, through the Intergovernmental Relations Body, to DOTr, CAAP, the contractor, airport management and the media. Authored by MP Baileng S. Mantawil, MP Mary Ann M. Arnado, MP Sha Elijah B. Dumama-Alba and MP Eddie M. Alih. Adopted on 19 January 2023.
Why it was proposed
CAAP's own project status report shows the expansion of the Cotabato passenger terminal started on 29 September 2020 and was due on 1 August 2021, then moved to 4 December 2021. As of June 2022 CAAP's website put it at 64.94% complete, with liquidated damages of ₱23,636.12 for every day of delay. The authors say the delay inconveniences travellers, poses a potential health hazard and hampers airport operations.
Who it affects
- Travellers using Cotabato Airport.
- The renovation contractor, whom the resolution wants held to account.
Who would implement it
- Department of Transportation
- Civil Aviation Authority of the Philippines
- Intergovernmental Relations Body
Funding
No appropriation. The resolution appropriates nothing.
What changes if it becomes law
- Nothing binding. DOTr and CAAP are national agencies the BTA cannot direct; the resolution urges.
- Copies go to DOTr, CAAP, the contractor, airport management and the media through the Intergovernmental Relations Body.
Raised during deliberations
- 19 January 2023: MP Mawallil asked about the status and cost of the renovation; MP Mantawil said the DOTr project was funded under the 2019 GAA at ₱41,427,313.00, started 29 September 2020, was due 1 August 2021, and stood at only 75.81% complete when work stopped on 4 December 2021.
- 19 January 2023: MP Mantawil listed the causes of delay from the DOTr status report: late delivery of materials, inadequate manpower, no contractor engineer on site and slow progress; MP Ampatuan added that the DOTr may take legal action against a contractor who fails its obligations.
- 19 January 2023: MP Tan asked about BARMM's role; MP Mantawil said it is a national government project implemented by the DOTr, with BARMM as beneficiary and the MOTC only facilitating, and there was no change of contractor.
- 19 January 2023: MP Loong (DM) noted that the Civil Aviation Authority of the Philippines conducted the bidding and moved to insert CAAP into the title and text, plus a whereas clause citing 64.94% completion as of June 2022 and liquidated damages of ₱23,636.12 per day of delay; accepted.
- 19 January 2023: Approved as amended, subject to style.
On the floor
- 19 January 2023Journal No. 16
Treated as a simple resolution; MP Mantawil delivered the authorship speech.
- 19 January 2023Journal No. 16
Interpellated by MPs Mawallil, Tan and Loong (DM).
- 19 January 2023Journal No. 16
MP Loong (DM)'s amendments adding the Civil Aviation Authority of the Philippines (CAAP) to the title and text were accepted by the author.
- 19 January 2023Journal No. 16
Approved as amended, subject to style.
What to notice
The figures come from CAAP's own reporting: 64.94% done as of June 2022, against a deadline that had already passed twice, with liquidated damages of ₱23,636.12 a day. The resolution does not name the contractor or the contract price and sets no date for a reply. Airports came up again: Resolution No. 398 (September 2023) invited CAAP and others to explain the status of Awang Airport's rehabilitation.